As part of the ongoing implementation of the equipment fabrication contract for the Alay Mahestan Petrochemical Project, AzarAb Industries has dispatched the first two pieces of process equipment following the successful completion of their fabrication.
The two vessels, designed for the sulphur injection drum system, mark the first equipment deliveries under the project.
Mohammadreza Nikazar, Project Manager, outlined the key specifications of the project, stating that the Alay Mahestan Petrochemical Project involves the development of a propane dehydrogenation (PDH) plant with an annual production capacity of 450,000 tonnes of polymer-grade propylene. The facility is currently under development in Bushehr Province, Iran.
He added that the project scope covers the fabrication of 26 process equipment items, with a total estimated weight of approximately 1,100 tonnes. The equipment comprises horizontal and vertical vessels, each weighing less than 120 tonnes.
Fabrication activities commenced at AzarAb Industries in February 2025, and, in accordance with the project schedule, the completion and delivery of all equipment are targeted for the end of 2026.
Highlighting the project's strategic importance to Iran's petrochemical industry, Nikazar noted that growing domestic demand for propylene and polypropylene, coupled with the availability of propane feedstock in the Assaluyeh region, underscores the importance of expanding downstream petrochemical capacities.
He emphasized that converting propane feedstock into higher-value products through downstream processing represents a significant opportunity to enhance value addition and strengthen the country's petrochemical value chain.